May 21, 2026
- Work began March 2nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling is scheduled for June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in early June.
Share May 21, 2026 on Facebook
Share May 21, 2026 on X (formerly Twitter)
Share May 21, 2026 on Linkedin
Email May 21, 2026 link
Project is substantially complete.