May 29, 2026

  • Edgewood Lane, Hill Road to Floating Feather Road
  • Work began March 2 nd.
  • Edgewood Lane will be closed during construction.
  • Contractor is currently working on sidewalk improvements.
  • Milling is scheduled for June 1-2.
  • Asphalt paving is scheduled for June 3-5.
  • Work is anticipated to be complete in mid June.