September 17, 2026 - Goldenrod
Goldenrod Avenue, west end to Cloverdale Road
- Goldenrod will be closed during the project.
- Work began July 6th.
- Underground drainage improvements are complete.
- Concrete placements for curb, gutter, and sidewalk are nearly complete.
- Asphalt paving is scheduled for October 1st, 2nd, and 3rd.
Share September 17, 2026 - Goldenrod on Facebook
Share September 17, 2026 - Goldenrod on X (formerly Twitter)
Share September 17, 2026 - Goldenrod on Linkedin
Email September 17, 2026 - Goldenrod link