December 15, 2023

  • Work is on State Street, 2nd Street to east of 4th Street and the State Street/16th Street intersection. •
  • Electrical work ongoing – signal poles have been set. •
  • Striping complete.
  • Waiting on landscape repair (including bioretention beds) and signal install.
  • Ped ramp walkarounds and sidewalk repair behind curb lines remains. Crews still working.
  • Anticipate re-opening the road in mid/late December.
Share December 15, 2023 on Facebook Share December 15, 2023 on Twitter Share December 15, 2023 on Linkedin Email December 15, 2023 link

This project is substantially complete. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>