December 15, 2023
- Work is on State Street, 2nd Street to east of 4th Street and the State Street/16th Street intersection. •
- Electrical work ongoing – signal poles have been set. •
- Striping complete.
- Waiting on landscape repair (including bioretention beds) and signal install.
- Ped ramp walkarounds and sidewalk repair behind curb lines remains. Crews still working.
- Anticipate re-opening the road in mid/late December.