2023 State Street Improvements: State and 16th/ State, 4th to 2nd

Share 2023 State Street Improvements: State and 16th/ State, 4th to 2nd on Facebook Share 2023 State Street Improvements: State and 16th/ State, 4th to 2nd on Twitter Share 2023 State Street Improvements: State and 16th/ State, 4th to 2nd on Linkedin Email 2023 State Street Improvements: State and 16th/ State, 4th to 2nd link

The Ada County Highway District (ACHD) will be constructing improvements to the State Street and 16th Street intersection and State Street from east of 4th Street to 2nd Street starting as early as late late March.* Work is expected to be complete by Summer 2024.

Project Description

  • Reconstruct both the State Street & 16th Street intersection and State St., east of 4th Street to 2nd Street
  • Complete traffic signal work at State Street & 16th Street
  • Add bioretention curb extensions and updated pedestrian ramps to both segments of State Street
  • As part of this project, ACHD will also be adding dual enhanced pedestrian crossings with bike push buttons across State Street at 3rd Street

Traffic and Construction Impacts

  • When the street isn’t closed, traffic flow will be prioritized during heavy commute times in the mornings and evenings. Crews will work 9 a.m.- 4 p.m. during the day and 8 p.m.-5 a.m. at night.
  • Night and weekend work is to be expected.
  • Crews may work 24 hours a day when blocks are fully closed, though night work will be evaluated for each location and must be pre-approved by ACHD.
  • One travel lane in each direction will remain open unless the street segment is completely closed.
  • Temporary pedestrian and bicyclist detours.
  • Temporary on-street parking impacts.
  • General construction noise, including equipment backup alarms, dust and ground vibration.
  • The contractor will coordinate with property and business owners to maintain access or provide alternative access.

*The construction schedule could change due to contractor staffing issues and supply-chain shortages.

The Ada County Highway District (ACHD) will be constructing improvements to the State Street and 16th Street intersection and State Street from east of 4th Street to 2nd Street starting as early as late late March.* Work is expected to be complete by Summer 2024.

Project Description

  • Reconstruct both the State Street & 16th Street intersection and State St., east of 4th Street to 2nd Street
  • Complete traffic signal work at State Street & 16th Street
  • Add bioretention curb extensions and updated pedestrian ramps to both segments of State Street
  • As part of this project, ACHD will also be adding dual enhanced pedestrian crossings with bike push buttons across State Street at 3rd Street

Traffic and Construction Impacts

  • When the street isn’t closed, traffic flow will be prioritized during heavy commute times in the mornings and evenings. Crews will work 9 a.m.- 4 p.m. during the day and 8 p.m.-5 a.m. at night.
  • Night and weekend work is to be expected.
  • Crews may work 24 hours a day when blocks are fully closed, though night work will be evaluated for each location and must be pre-approved by ACHD.
  • One travel lane in each direction will remain open unless the street segment is completely closed.
  • Temporary pedestrian and bicyclist detours.
  • Temporary on-street parking impacts.
  • General construction noise, including equipment backup alarms, dust and ground vibration.
  • The contractor will coordinate with property and business owners to maintain access or provide alternative access.

*The construction schedule could change due to contractor staffing issues and supply-chain shortages.

  • July 26, 2024

    Share July 26, 2024 on Facebook Share July 26, 2024 on Twitter Share July 26, 2024 on Linkedin Email July 26, 2024 link
    • State Street, 2nd Street to east of 4th Street - Complete.
    • State Street/16th Street intersection - Paving complete. Concrete complete. Signal work and lane lines remain – targeting intersection reopening on July 31st.
  • July 19, 2024

    Share July 19, 2024 on Facebook Share July 19, 2024 on Twitter Share July 19, 2024 on Linkedin Email July 19, 2024 link
    • State Street, 2nd Street to east of 4th Street - Complete.
    • State Street/16th Street intersection - Paving complete.
      • Concrete complete.
      • Signal work and lane lines remain – targeting intersection reopening on July 31st.
  • July 12, 2024

    Share July 12, 2024 on Facebook Share July 12, 2024 on Twitter Share July 12, 2024 on Linkedin Email July 12, 2024 link
    • State Street, 2nd Street to east of 4th Street - Complete.
    • State Street/16th Street intersection - South side of road has been paved.
    • Concrete prep and placements ongoing.
    • Contractor is planning to pave the north side of State Street on Friday.
  • June 28, 2024

    Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link
    • State Street, 2nd Street to east of 4th Street - Complete.
    • State Street/16th Street intersection - South side of road has been paved. Curb and gutter concrete was placed on June 12th.
  • June 21, 2024

    Share June 21, 2024 on Facebook Share June 21, 2024 on Twitter Share June 21, 2024 on Linkedin Email June 21, 2024 link
    • State Street, 2nd Street to east of 4th Street - Complete.
    • State Street/16th Street intersection - South side of road has been paved. Curb and gutter concrete was placed on June 12th
  • June 14, 2024

    Share June 14, 2024 on Facebook Share June 14, 2024 on Twitter Share June 14, 2024 on Linkedin Email June 14, 2024 link
    • State Street, 2nd Street to east of 4th Street
      • Complete
    • State Street/16th Street intersection
      • South side of road is prepped and ready for paving.
      • Curb and gutter concrete was placed on June 12th
  • June 7, 2024

    Share June 7, 2024 on Facebook Share June 7, 2024 on Twitter Share June 7, 2024 on Linkedin Email June 7, 2024 link
    • State Street, 2nd Street to east of 4th Street
      • Complete
    • State Street/16th Street intersection
      • Electrical contractor is complete with underground work
      • Fiber swap – Complete
      • Poles have been placed
      • Concrete prep continues
      • Sawcutting for pavement removal started June 4th
  • May 31, 2024

    Share May 31, 2024 on Facebook Share May 31, 2024 on Twitter Share May 31, 2024 on Linkedin Email May 31, 2024 link
    • State Street, 2nd Street to east of 4th Street - Complete.
    • State Street/16th Street intersection - Electrical contractor is complete with underground work.
    • Fiber swap – Complete.
    • Poles have been placed.
    • Concrete prep starting this week.
  • May 16, 2024

    Share May 16, 2024 on Facebook Share May 16, 2024 on Twitter Share May 16, 2024 on Linkedin Email May 16, 2024 link
    • State Street, 2nd Street to east of 4th Street - Complete.
    • State Street/16th Street intersection - Electrical contractor is complete with underground. Waiting for fiber swap – scheduled for May 18th o Poles have been placed.
  • May 10, 2024

    Share May 10, 2024 on Facebook Share May 10, 2024 on Twitter Share May 10, 2024 on Linkedin Email May 10, 2024 link
    • State Street, 2nd Street to east of 4th Street - Complete.
    • State Street/16th Street intersection - Electrical contractor is complete with underground. Waiting for fiber swap. Pole bases have been placed.
Page last updated: 26 Jul 2024, 09:45 AM