December 22, 2023

  • State Street, 2nd Street to east of 4th Street
    • Electrical work complete.
    • Waiting on landscape repair (including bioretention beds) and signal install.
    • Ped ramp walkarounds and sidewalk repair behind curb lines remains. Crews still working.
    • Anticipate re-opening the road in late December.
Share December 22, 2023 on Facebook Share December 22, 2023 on X (formerly Twitter) Share December 22, 2023 on Linkedin Email December 22, 2023 link

This project is substantially complete. 