December 8, 2023

  • Work is on State Street, 2nd Street to east of 4th Street and the State Street/16th Street intersection.
  • Electrical work ongoing - prepped for signal poles after paving is complete.
  • Striping complete.
  • Waiting on landscape repair (including bioretention beds) and signal install.
  • Ped ramp walkarounds and sidewalk repair behind curb lines remains.
  • Crews on site December 6th.
  • Anticipate re-opening the road in mid/late December.
Share December 8, 2023 on Facebook Share December 8, 2023 on Twitter Share December 8, 2023 on Linkedin Email December 8, 2023 link

This project is substantially complete. 