December 8, 2023
- Work is on State Street, 2nd Street to east of 4th Street and the State Street/16th Street intersection.
- Electrical work ongoing - prepped for signal poles after paving is complete.
- Striping complete.
- Waiting on landscape repair (including bioretention beds) and signal install.
- Ped ramp walkarounds and sidewalk repair behind curb lines remains.
- Crews on site December 6th.
- Anticipate re-opening the road in mid/late December.
Share December 8, 2023 on Facebook
Share December 8, 2023 on Twitter
Share December 8, 2023 on Linkedin
Email December 8, 2023 link
This project is substantially complete.