January 19, 2024
- State Street, 2nd Street to east of 4th Street - Minor concrete placements continue under flagging operations.
- Minor stripe work remains at ped crossings.
- Landscape repair ongoing - weather dependent.
- State Street/16th Street intersection - Planning to start in February.
Share January 19, 2024 on Facebook
Share January 19, 2024 on Twitter
Share January 19, 2024 on Linkedin
Email January 19, 2024 link
This project is substantially complete.