January 26, 2024

  • State Street, 2nd Street to east of 4th Street - Minor concrete placements continue under flagging operations.
  • Minor stripe work remains at ped crossings.
  • Landscape repair ongoing- weather dependent.
  • State Street/16th Street intersection - Planning to start in February.
Share January 26, 2024 on Facebook Share January 26, 2024 on X (formerly Twitter) Share January 26, 2024 on Linkedin Email January 26, 2024 link

This project is substantially complete. 