  • State Street, 2nd Street to east of 4th Street - Electrical work complete. Waiting on landscape repair (including bioretention beds) and signal install.
  • Ped ramp walkarounds and sidewalk repair behind curb lines complete.
  • Road has been re-opened.
  • Minor concrete placements continue under flagging operations. State Street/16th Street intersection.
Share January 5, 2024 on Facebook Share January 5, 2024 on Twitter Share January 5, 2024 on Linkedin Email January 5, 2024 link

This project is substantially complete. 