January 5, 2024

  • State Street, 2nd Street to east of 4th Street - Electrical work complete. Waiting on landscape repair (including bioretention beds) and signal install.
  • Ped ramp walkarounds and sidewalk repair behind curb lines complete.
  • Road has been re-opened.
  • Minor concrete placements continue under flagging operations. State Street/16th Street intersection.
Share January 5, 2024 on Facebook Share January 5, 2024 on X (formerly Twitter) Share January 5, 2024 on Linkedin Email January 5, 2024 link

This project is substantially complete. 