July 12, 2024
- State Street, 2nd Street to east of 4th Street - Complete.
- State Street/16th Street intersection - South side of road has been paved.
- Concrete prep and placements ongoing.
- Contractor is planning to pave the north side of State Street on Friday.
Share July 12, 2024 on Facebook
Share July 12, 2024 on Twitter
Share July 12, 2024 on Linkedin
Email July 12, 2024 link
This project is substantially complete.