July 19, 2024

  • State Street, 2nd Street to east of 4th Street - Complete.
  • State Street/16th Street intersection - Paving complete.
    • Concrete complete.
    • Signal work and lane lines remain – targeting intersection reopening on July 31st.
Share July 19, 2024 on Facebook Share July 19, 2024 on X (formerly Twitter) Share July 19, 2024 on Linkedin Email July 19, 2024 link

This project is substantially complete. 