June 7, 2024
- State Street, 2nd Street to east of 4th Street
- Complete
- State Street/16th Street intersection
- Electrical contractor is complete with underground work
- Fiber swap – Complete
- Poles have been placed
- Concrete prep continues
- Sawcutting for pavement removal started June 4th
Share June 7, 2024 on Facebook
Share June 7, 2024 on Twitter
Share June 7, 2024 on Linkedin
Email June 7, 2024 link
This project is substantially complete.