November 17, 2023

  • Work is on State Street, 2nd Street to east of 4th Street and the State Street/16th Street intersection.
    • Curb placed
    • Paving 11/16-11/17
    • Electrical work ongoing - prepped for signal poles after paving is complete.
    • Striping is scheduled for 11/21
Share November 17, 2023 on Facebook Share November 17, 2023 on Twitter Share November 17, 2023 on Linkedin Email November 17, 2023 link

This project is substantially complete. 