Work is on State Street, 2nd Street to east of 4th Street and the State Street/16th Street intersection.

  • Curbing is complete.
  • Paving complete.
  • Electrical work ongoing - prepped for signal poles after paving is complete.
  • Striping complete.
  • Anticipate re-opening the road early December after signals are installed.
Share November 22, 2023 on Facebook Share November 22, 2023 on Twitter Share November 22, 2023 on Linkedin Email November 22, 2023 link

This project is substantially complete. 