November 9, 2023

  • Roadway has been milled to design depth.
  • Demo and grade prep complete on 2nd and 3rd Street.
  • Fiber utility work complete.
  • Curb prep at ped ramps continues.
  • Electrical work ongoing at State and 3rd - prepped for signal poles.
Share November 9, 2023 on Facebook Share November 9, 2023 on Twitter Share November 9, 2023 on Linkedin Email November 9, 2023 link

This project is substantially complete. 