August 14, 2026
Shoreline Dr, Americana Blvd to Fairview Ave
- Signal work at Americana & Shoreline is anticipated to begin August 24th and take 3-4 weeks to complete.
- Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping is complete.
- Shoreline was re-opened for right-in and right-out only traffic on August 4th and will remain in this configuration until the new traffic signal is complete.
Eisenman Rd, Gowen Rd to 2000’ South
- ACHD’s project started August 5th.
- Eisenman Rd will remain open for the ACHD project.
- Milling started August 7th.
- Asphalt paving started August 11th.
- Veolia’s work to replace the water line is complete.
Eisenman Rd, Freight St to I-84
- Work is scheduled to start in late August or early September. Eisenman Road will be closed for this portion of the ACHD project.
Share August 14, 2026 on Facebook
Share August 14, 2026 on X (formerly Twitter)
Share August 14, 2026 on Linkedin
Email August 14, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends