August 14, 2026

Shoreline Dr, Americana Blvd to Fairview Ave

  • Signal work at Americana & Shoreline is anticipated to begin August 24th and take 3-4 weeks to complete.
  • Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
  • Concrete sidewalk improvements are complete until signal materials arrive.
  • Milling, paving, and striping is complete.
  • Shoreline was re-opened for right-in and right-out only traffic on August 4th and will remain in this configuration until the new traffic signal is complete.

Eisenman Rd, Gowen Rd to 2000’ South

  • ACHD’s project started August 5th.
  • Eisenman Rd will remain open for the ACHD project.
  • Milling started August 7th.
  • Asphalt paving started August 11th.
  • Veolia’s work to replace the water line is complete.

Eisenman Rd, Freight St to I-84

  • Work is scheduled to start in late August or early September. Eisenman Road will be closed for this portion of the ACHD project.