Americana Boulevard | Shoreline Drive | Eisenman Road

Share Americana Boulevard | Shoreline Drive | Eisenman Road on Facebook Share Americana Boulevard | Shoreline Drive | Eisenman Road on X (formerly Twitter) Share Americana Boulevard | Shoreline Drive | Eisenman Road on Linkedin Email Americana Boulevard | Shoreline Drive | Eisenman Road link

The Ada County Highway District (ACHD) will be rehabilitating several streets in your area as part of a federally funded project to improve pavement conditions and upgrade the streets for all users.

As part of the street reconstruction, ACHD will upgrade select pedestrian ramps and driveways to meet current Americans with Disabilities Act (ADA) standards. The work also includes improvements for people walking and biking, such as improved crossings and bike lane enhancements. These changes are intended to improve safety and accessibility for everyone using the street.

Project Descriptions

Eisenman Road

Eisenman Road, Gowen Road to 2000 feet south of Gowen Road

  • Removing and replacing pavement

  • Upgrading pedestrian ramps and driveways for current ADA compliance

  • The existing Gowen Road intersection signal will not be impacted

Eisenman Road, Freight Street to East Bound I-84 Offramp

  • Removing and replacing pavement

Americana Boulevard

Americana Boulevard, Ann Morrison Park Boulevard to Shoreline Drive

  • Removing and replacing pavement

  • Upgrading pedestrian ramps and driveways for current ADA compliance

  • Traffic signals at Ann Morrison Park Boulevard and Shoreline Drive will be updated for current Accessible Pedestrian Signal (APS) compliance

  • Maintaining the existing roadway configuration of two lanes in each direction with a center turn lane and bike lanes

  • Constructing protected intersection treatment at Shoreline Drive intersection to enhance pedestrian and bicyclist accessibility and safety at the crossings

  • Constructing drainage improvements within the existing right-of-way to treat stormwater

Shoreline Drive

Shoreline Drive, Americana Boulevard to Fairview Avenue

  • Removing and replacing pavement

  • Upgrading pedestrian ramps and driveways for current ADA compliance

  • Improving existing bike lanes with raised buffer medians

  • Installing a Rectangular Rapid Flashing Beacon (RRFB) at the entrance to the firefighter memorial entrance

  • The existing traffic signal at Fairview Avenue will not be impacted

The Ada County Highway District (ACHD) will be rehabilitating several streets in your area as part of a federally funded project to improve pavement conditions and upgrade the streets for all users.

As part of the street reconstruction, ACHD will upgrade select pedestrian ramps and driveways to meet current Americans with Disabilities Act (ADA) standards. The work also includes improvements for people walking and biking, such as improved crossings and bike lane enhancements. These changes are intended to improve safety and accessibility for everyone using the street.

Project Descriptions

Eisenman Road

Eisenman Road, Gowen Road to 2000 feet south of Gowen Road

  • Removing and replacing pavement

  • Upgrading pedestrian ramps and driveways for current ADA compliance

  • The existing Gowen Road intersection signal will not be impacted

Eisenman Road, Freight Street to East Bound I-84 Offramp

  • Removing and replacing pavement

Americana Boulevard

Americana Boulevard, Ann Morrison Park Boulevard to Shoreline Drive

  • Removing and replacing pavement

  • Upgrading pedestrian ramps and driveways for current ADA compliance

  • Traffic signals at Ann Morrison Park Boulevard and Shoreline Drive will be updated for current Accessible Pedestrian Signal (APS) compliance

  • Maintaining the existing roadway configuration of two lanes in each direction with a center turn lane and bike lanes

  • Constructing protected intersection treatment at Shoreline Drive intersection to enhance pedestrian and bicyclist accessibility and safety at the crossings

  • Constructing drainage improvements within the existing right-of-way to treat stormwater

Shoreline Drive

Shoreline Drive, Americana Boulevard to Fairview Avenue

  • Removing and replacing pavement

  • Upgrading pedestrian ramps and driveways for current ADA compliance

  • Improving existing bike lanes with raised buffer medians

  • Installing a Rectangular Rapid Flashing Beacon (RRFB) at the entrance to the firefighter memorial entrance

  • The existing traffic signal at Fairview Avenue will not be impacted

  • August 20, 2026

    Share August 20, 2026 on Facebook Share August 20, 2026 on X (formerly Twitter) Share August 20, 2026 on Linkedin Email August 20, 2026 link

    Shoreline Dr, Americana Blvd to Fairview Ave

    • Signal work at Americana & Shoreline is anticipated to begin August 24th and take 3-4 weeks to complete.
    • Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping is complete.
    • The west leg of Shoreline will remain open to right-in and right-out only traffic and will remain in this configuration until the new traffic signal is complete.
    • The east leg of Shoreline will be closed beginning August 24th for the signal work.

    Eisenman Rd, Gowen Rd to 2000’ South

    • ACHD’s project started August 5th.
    • Eisenman Rd will remain open for the ACHD project.
    • Milling and paving on the east side are complete.
    • Milling and paving on the west side is anticipated to be complete on August 21st.
    • After paving is complete, minor work remains – striping, manhole adjustments, etc.
    • Veolia’s work to replace the water line is complete.

    Eisenman Rd, Freight St to I-84 - Work is scheduled to start as early as August 24th. Eisenman Road will remain open for the work.


    Shoreline Dr, Americana Blvd to Fairview Ave

    • Signal work at Americana & Shoreline is anticipated to begin August 24th and take 3-4 weeks to complete.
    • Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping is complete.
    • The west leg of Shoreline will remain open to right-in and right-out only traffic and will remain in this configuration until the new traffic signal is complete.
    • The east leg of Shoreline will be closed beginning August 24th for the signal work.

    Eisenman Rd, Gowen Rd to 2000’ South

    • ACHD’s project started August 5th.
    • Eisenman Rd will remain open for the ACHD project.
    • Milling and paving on the east side are complete.
    • Milling and paving on the west side is anticipated to be complete on August 21st.
    • After paving is complete, minor work remains – striping, manhole adjustments, etc.
    • Veolia’s work to replace the water line is complete.

    Eisenman Rd, Freight St to I-84 - Work is scheduled to start as early as August 24th. Eisenman Road will remain open for the work.


  • August 14, 2026

    Share August 14, 2026 on Facebook Share August 14, 2026 on X (formerly Twitter) Share August 14, 2026 on Linkedin Email August 14, 2026 link

    Shoreline Dr, Americana Blvd to Fairview Ave

    • Signal work at Americana & Shoreline is anticipated to begin August 24th and take 3-4 weeks to complete.
    • Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping is complete.
    • Shoreline was re-opened for right-in and right-out only traffic on August 4th and will remain in this configuration until the new traffic signal is complete.

    Eisenman Rd, Gowen Rd to 2000’ South

    • ACHD’s project started August 5th.
    • Eisenman Rd will remain open for the ACHD project.
    • Milling started August 7th.
    • Asphalt paving started August 11th.
    • Veolia’s work to replace the water line is complete.

    Eisenman Rd, Freight St to I-84

    • Work is scheduled to start in late August or early September. Eisenman Road will be closed for this portion of the ACHD project.



    Shoreline Dr, Americana Blvd to Fairview Ave

    • Signal work at Americana & Shoreline is anticipated to begin August 24th and take 3-4 weeks to complete.
    • Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping is complete.
    • Shoreline was re-opened for right-in and right-out only traffic on August 4th and will remain in this configuration until the new traffic signal is complete.

    Eisenman Rd, Gowen Rd to 2000’ South

    • ACHD’s project started August 5th.
    • Eisenman Rd will remain open for the ACHD project.
    • Milling started August 7th.
    • Asphalt paving started August 11th.
    • Veolia’s work to replace the water line is complete.

    Eisenman Rd, Freight St to I-84

    • Work is scheduled to start in late August or early September. Eisenman Road will be closed for this portion of the ACHD project.



  • August 7, 2026

    Share August 7, 2026 on Facebook Share August 7, 2026 on X (formerly Twitter) Share August 7, 2026 on Linkedin Email August 7, 2026 link

    Project includes work on the following segments:

    • Americana Blvd, Ann Morrison Park Blvd to Shoreline Dr
      • Shoreline Dr, Americana Blvd to Fairview Ave
      • Electrical work for new traffic signals is on-going. Waiting for signal materials to be delivered later this year.
      • Concrete sidewalk improvements are complete until signal materials arrive.
      • Milling, paving, and striping is complete
      • Shoreline was re-opened for right-in and right-out only traffic on August 4th and will remain in this configuration until the new traffic signal is complete.
    • Eisenman Rd, Gowen Rd to 2000’ South
      • ACHD’s project started August 5th. Eisenman Rd will remain open for the ACHD project.
      • Veolia’s work to replace the water line is complete.
    • Eisenman Rd, Freight St to I-84
      • Work is scheduled to start in late August or early September. Eisenman Road will be closed for this portion of the ACHD project.

    Project includes work on the following segments:

    • Americana Blvd, Ann Morrison Park Blvd to Shoreline Dr
      • Shoreline Dr, Americana Blvd to Fairview Ave
      • Electrical work for new traffic signals is on-going. Waiting for signal materials to be delivered later this year.
      • Concrete sidewalk improvements are complete until signal materials arrive.
      • Milling, paving, and striping is complete
      • Shoreline was re-opened for right-in and right-out only traffic on August 4th and will remain in this configuration until the new traffic signal is complete.
    • Eisenman Rd, Gowen Rd to 2000’ South
      • ACHD’s project started August 5th. Eisenman Rd will remain open for the ACHD project.
      • Veolia’s work to replace the water line is complete.
    • Eisenman Rd, Freight St to I-84
      • Work is scheduled to start in late August or early September. Eisenman Road will be closed for this portion of the ACHD project.
  • July 30, 2026

    Share July 30, 2026 on Facebook Share July 30, 2026 on X (formerly Twitter) Share July 30, 2026 on Linkedin Email July 30, 2026 link

    Shoreline Dr, Americana Blvd to Fairview Ave

    • Electrical work for new traffic signals is on-going.
    • Waiting for signal materials to be delivered later this year.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping is complete.
    • Shoreline will be re-opened for right-in and right-out only traffic on August 4th and remain in this configuration until the new traffic signal is complete.

    Eisenman Rd, Gowen Rd to 2000’ South

    • ACHD’s project is anticipated to start August 5th.
    • Eisenman Road will remain open for the ACHD project.
    • Veolia is replacing the water line in advance of the project.
    • Eisenman Road is closed for their work, anticipated to re-open on August 4th.

    Shoreline Dr, Americana Blvd to Fairview Ave

    • Electrical work for new traffic signals is on-going.
    • Waiting for signal materials to be delivered later this year.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping is complete.
    • Shoreline will be re-opened for right-in and right-out only traffic on August 4th and remain in this configuration until the new traffic signal is complete.

    Eisenman Rd, Gowen Rd to 2000’ South

    • ACHD’s project is anticipated to start August 5th.
    • Eisenman Road will remain open for the ACHD project.
    • Veolia is replacing the water line in advance of the project.
    • Eisenman Road is closed for their work, anticipated to re-open on August 4th.
  • July 23, 2026

    Share July 23, 2026 on Facebook Share July 23, 2026 on X (formerly Twitter) Share July 23, 2026 on Linkedin Email July 23, 2026 link


    Shoreline Dr, Americana Blvd to Fairview Ave

    • Electrical work for new traffic signals is on-going.
    • Waiting for signal materials to be delivered later this year.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping is complete.
    • Shoreline will be re-opened for right-in and right-out only traffic until the new traffic signal is complete.


    Shoreline Dr, Americana Blvd to Fairview Ave

    • Electrical work for new traffic signals is on-going.
    • Waiting for signal materials to be delivered later this year.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping is complete.
    • Shoreline will be re-opened for right-in and right-out only traffic until the new traffic signal is complete.
  • July 17, 2026

    Share July 17, 2026 on Facebook Share July 17, 2026 on X (formerly Twitter) Share July 17, 2026 on Linkedin Email July 17, 2026 link

    Americana Blvd, Ann Morrison Park Blvd to Shoreline Dr.

    • Work started Thursday, April 16th.
    • Americana will remain open during the project but will be reduced to one lane in each direction.
    • Electrical work for new traffic signals is on-going. Waiting for signal materials to be delivered later this year.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping is complete.

    Shoreline Dr, Americana Blvd to Fairview Ave.

    • Shoreline is closed east and west of Americana during the project.
    • Electrical work is on-going for a pedestrian crossing at the Firefighters Memorial.
    • Concrete sidewalk improvements are complete.
    • Concrete for roadway islands is on-going.
    • Milling, paving, and striping is complete.

    Americana Blvd, Ann Morrison Park Blvd to Shoreline Dr.

    • Work started Thursday, April 16th.
    • Americana will remain open during the project but will be reduced to one lane in each direction.
    • Electrical work for new traffic signals is on-going. Waiting for signal materials to be delivered later this year.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping is complete.

    Shoreline Dr, Americana Blvd to Fairview Ave.

    • Shoreline is closed east and west of Americana during the project.
    • Electrical work is on-going for a pedestrian crossing at the Firefighters Memorial.
    • Concrete sidewalk improvements are complete.
    • Concrete for roadway islands is on-going.
    • Milling, paving, and striping is complete.
  • July 9, 2026

    Share July 9, 2026 on Facebook Share July 9, 2026 on X (formerly Twitter) Share July 9, 2026 on Linkedin Email July 9, 2026 link

    Americana Blvd, Ann Morrison Park Blvd to Shoreline Dr

    • Work started Thursday, April 16th.
    • Americana will remain open during the project but will be reduced to one lane in each direction.
    • Electrical work for new traffic signals is on-going.
    • Waiting for signal materials to be delivered later this year.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping is complete.

    Shoreline Dr, Americana Blvd to Fairview Ave

    • Shoreline is closed east and west of Americana during the project.
    • Electrical work is on-going for a pedestrian crossing at the Firefighters Memorial.
    • Concrete sidewalk improvements are complete.
    • Concrete for roadway islands is on-going.
    • Milling, paving, and striping is complete.


    Americana Blvd, Ann Morrison Park Blvd to Shoreline Dr

    • Work started Thursday, April 16th.
    • Americana will remain open during the project but will be reduced to one lane in each direction.
    • Electrical work for new traffic signals is on-going.
    • Waiting for signal materials to be delivered later this year.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping is complete.

    Shoreline Dr, Americana Blvd to Fairview Ave

    • Shoreline is closed east and west of Americana during the project.
    • Electrical work is on-going for a pedestrian crossing at the Firefighters Memorial.
    • Concrete sidewalk improvements are complete.
    • Concrete for roadway islands is on-going.
    • Milling, paving, and striping is complete.


  • July 1, 2026

    Share July 1, 2026 on Facebook Share July 1, 2026 on X (formerly Twitter) Share July 1, 2026 on Linkedin Email July 1, 2026 link

    Americana Blvd, Ann Morrison Park Blvd to Shoreline Dr

    • Work started Thursday, April 16th.
    • Americana will remain open during the project but will be reduced to one lane in each direction.
    • Electrical work for new traffic signals is on-going. Waiting for signal materials to be delivered later this summer.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping is complete.

    Shoreline Dr, Americana Blvd to Fairview Ave

    • Shoreline is closed east and west of Americana during the project.
    • Electrical work is on-going for a pedestrian crossing at the Firefighters Memorial.
    • Concrete sidewalk improvements are complete.
    • Concrete for roadway islands is on-going.
    • Milling, paving, and striping is complete.


    Americana Blvd, Ann Morrison Park Blvd to Shoreline Dr

    • Work started Thursday, April 16th.
    • Americana will remain open during the project but will be reduced to one lane in each direction.
    • Electrical work for new traffic signals is on-going. Waiting for signal materials to be delivered later this summer.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping is complete.

    Shoreline Dr, Americana Blvd to Fairview Ave

    • Shoreline is closed east and west of Americana during the project.
    • Electrical work is on-going for a pedestrian crossing at the Firefighters Memorial.
    • Concrete sidewalk improvements are complete.
    • Concrete for roadway islands is on-going.
    • Milling, paving, and striping is complete.


  • June 26, 2026

    Share June 26, 2026 on Facebook Share June 26, 2026 on X (formerly Twitter) Share June 26, 2026 on Linkedin Email June 26, 2026 link

    Americana Blvd, Ann Morrison Park Blvd to Shoreline Dr

    • Work started Thursday, April 16th.
    • Americana will remain open during the project but will be reduced to one lane in each direction.
    • Electrical work for new traffic signals is on-going.
    • Concrete sidewalk improvements are on-going.
    • Milling, paving, and striping is complete.

    Shoreline Dr, Americana Blvd to Fairview Ave

    • Shoreline is closed east and west of Americana during the project.
    • Electrical work is on-going for a pedestrian crossing at the Firefighters Memorial.
    • Concrete sidewalk improvements are on-going.
    • Milling, paving, and striping is complete.


    Americana Blvd, Ann Morrison Park Blvd to Shoreline Dr

    • Work started Thursday, April 16th.
    • Americana will remain open during the project but will be reduced to one lane in each direction.
    • Electrical work for new traffic signals is on-going.
    • Concrete sidewalk improvements are on-going.
    • Milling, paving, and striping is complete.

    Shoreline Dr, Americana Blvd to Fairview Ave

    • Shoreline is closed east and west of Americana during the project.
    • Electrical work is on-going for a pedestrian crossing at the Firefighters Memorial.
    • Concrete sidewalk improvements are on-going.
    • Milling, paving, and striping is complete.


  • June 18, 2026

    Share June 18, 2026 on Facebook Share June 18, 2026 on X (formerly Twitter) Share June 18, 2026 on Linkedin Email June 18, 2026 link

    Americana Blvd, Ann Morrison Park Blvd to Shoreline Dr

    • Work started Thursday, April 16th.
    • Americana will remain open during the project but will be reduced to one lane in each direction.
    • Electrical work for new traffic signals is on-going.
    • Concrete sidewalk improvements are on-going.
    • Milling and paving is complete.

    Shoreline Dr, Americana Blvd to Fairview Ave

    • Shoreline is closed east and west of Americana during the project.
    • Electrical work is on-going for a pedestrian crossing at the Firefighters Memorial.
    • Concrete sidewalk improvements are on-going.
    • Milling and paving is complete.

    Americana Blvd, Ann Morrison Park Blvd to Shoreline Dr

    • Work started Thursday, April 16th.
    • Americana will remain open during the project but will be reduced to one lane in each direction.
    • Electrical work for new traffic signals is on-going.
    • Concrete sidewalk improvements are on-going.
    • Milling and paving is complete.

    Shoreline Dr, Americana Blvd to Fairview Ave

    • Shoreline is closed east and west of Americana during the project.
    • Electrical work is on-going for a pedestrian crossing at the Firefighters Memorial.
    • Concrete sidewalk improvements are on-going.
    • Milling and paving is complete.
Page last updated: 20 Aug 2026, 04:00 PM