August 20, 2026

Shoreline Dr, Americana Blvd to Fairview Ave

  • Signal work at Americana & Shoreline is anticipated to begin August 24th and take 3-4 weeks to complete.
  • Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
  • Concrete sidewalk improvements are complete until signal materials arrive.
  • Milling, paving, and striping is complete.
  • The west leg of Shoreline will remain open to right-in and right-out only traffic and will remain in this configuration until the new traffic signal is complete.
  • The east leg of Shoreline will be closed beginning August 24th for the signal work.

Eisenman Rd, Gowen Rd to 2000’ South

  • ACHD’s project started August 5th.
  • Eisenman Rd will remain open for the ACHD project.
  • Milling and paving on the east side are complete.
  • Milling and paving on the west side is anticipated to be complete on August 21st.
  • After paving is complete, minor work remains – striping, manhole adjustments, etc.
  • Veolia’s work to replace the water line is complete.

Eisenman Rd, Freight St to I-84 - Work is scheduled to start as early as August 24th. Eisenman Road will remain open for the work.