August 20, 2026
Shoreline Dr, Americana Blvd to Fairview Ave
- Signal work at Americana & Shoreline is anticipated to begin August 24th and take 3-4 weeks to complete.
- Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping is complete.
- The west leg of Shoreline will remain open to right-in and right-out only traffic and will remain in this configuration until the new traffic signal is complete.
- The east leg of Shoreline will be closed beginning August 24th for the signal work.
Eisenman Rd, Gowen Rd to 2000’ South
- ACHD’s project started August 5th.
- Eisenman Rd will remain open for the ACHD project.
- Milling and paving on the east side are complete.
- Milling and paving on the west side is anticipated to be complete on August 21st.
- After paving is complete, minor work remains – striping, manhole adjustments, etc.
- Veolia’s work to replace the water line is complete.
Eisenman Rd, Freight St to I-84 - Work is scheduled to start as early as August 24th. Eisenman Road will remain open for the work.
Share August 20, 2026 on Facebook
Share August 20, 2026 on X (formerly Twitter)
Share August 20, 2026 on Linkedin
Email August 20, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends