August 28, 2026
- Shoreline Dr, Americana Blvd to Fairview Ave
- Signal work at Americana & Shoreline began August 24th and will take 3-4 weeks to complete.
- Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping are complete.
- The west leg of Shoreline will remain open to right-in and right-out only traffic and will remain in this configuration until the new traffic signal is complete.
- The east leg of Shoreline was closed August 24th for the signal work.
- Eisenman Rd, Gowen Rd to 2000’ South
- Milling and paving is complete.
- Minor work remains – striping, manhole adjustments, concrete sidewalk, etc.
- Veolia’s work to replace the water line is complete.
- Eisenman Rd, Freight St to I-84
- Work is started August 24th. Eisenman Road will remain open for the work.
- Milling and paving on the segment from Freight Street to the truck stop is complete.
- Mill and paving from the truck stop to I-84 will continue in early September. Work impacting I-84 will be done at night.
Share August 28, 2026 on Facebook
Share August 28, 2026 on X (formerly Twitter)
Share August 28, 2026 on Linkedin
Email August 28, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends