August 28, 2026

  • Shoreline Dr, Americana Blvd to Fairview Ave
    • Signal work at Americana & Shoreline began August 24th and will take 3-4 weeks to complete.
    • Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping are complete.
    • The west leg of Shoreline will remain open to right-in and right-out only traffic and will remain in this configuration until the new traffic signal is complete.
    • The east leg of Shoreline was closed August 24th for the signal work.
  • Eisenman Rd, Gowen Rd to 2000’ South
    • Milling and paving is complete.
    • Minor work remains – striping, manhole adjustments, concrete sidewalk, etc.
    • Veolia’s work to replace the water line is complete.
  • Eisenman Rd, Freight St to I-84
    • Work is started August 24th. Eisenman Road will remain open for the work.
    • Milling and paving on the segment from Freight Street to the truck stop is complete.
    • Mill and paving from the truck stop to I-84 will continue in early September. Work impacting I-84 will be done at night.