August 7, 2026

Project includes work on the following segments:

  • Americana Blvd, Ann Morrison Park Blvd to Shoreline Dr
    • Shoreline Dr, Americana Blvd to Fairview Ave
    • Electrical work for new traffic signals is on-going. Waiting for signal materials to be delivered later this year.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping is complete
    • Shoreline was re-opened for right-in and right-out only traffic on August 4th and will remain in this configuration until the new traffic signal is complete.
  • Eisenman Rd, Gowen Rd to 2000’ South
    • ACHD’s project started August 5th. Eisenman Rd will remain open for the ACHD project.
    • Veolia’s work to replace the water line is complete.
  • Eisenman Rd, Freight St to I-84
    • Work is scheduled to start in late August or early September. Eisenman Road will be closed for this portion of the ACHD project.