Shoreline Dr, Americana Blvd to Fairview Ave

  • Electrical work for new traffic signals is on-going.
  • Waiting for signal materials to be delivered later this year.
  • Concrete sidewalk improvements are complete until signal materials arrive.
  • Milling, paving, and striping is complete.
  • Shoreline will be re-opened for right-in and right-out only traffic until the new traffic signal is complete.