May 29, 2026

Americana Blvd, Ann Morrison Park Blvd to Shoreline Dr

  • Work started Thursday, April 16th.
  • Americana will remain open during the project but will be reduced to one lane in each direction.
  • Electrical work for new traffic signals is on-going.
  • Concrete sidewalk improvements are on-going.

Shoreline Dr, Americana Blvd to Fairview Ave

  • Shoreline is closed east and west of Americana during the project.
  • Electrical work is on-going for a pedestrian crossing at the Firefighters Memorial.
  • Concrete sidewalk improvements are on-going.