October 2, 2026

Shoreline Dr, Americana Blvd to Fairview Ave

  • The signal at Americana & Shoreline was activated Wednesday night, September 23rd.
  • Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
  • Concrete sidewalk improvements are complete until signal materials arrive.
  • Milling, paving, and striping are complete.