September 11, 2026 - Americana

  • Shoreline Dr, Americana Blvd to Fairview Ave
    • Signal work at Americana & Shoreline began August 24th and will take 3-4 weeks to complete.
    • Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
    • Concrete sidewalk improvements are complete until signal materials arrive.
    • Milling, paving, and striping are complete.
    • The west leg of Shoreline will remain open to right-in and right-out only traffic and will remain in this configuration until the new traffic signal is complete.
    • The east leg of Shoreline was closed August 24th for the signal work.