September 11, 2026 - Eisenman

Eisenman Rd, Gowen Rd to 2000’ South

  • Milling and paving is complete.
  • Veolia’s work to replace the water line is complete.

Eisenman Rd, Freight St to I-84

  • Work is started August 24th.
  • Eisenman Road will remain open for the work.
  • Milling and paving on the segment from Freight Street to the truck stop is complete.
  • Mill and paving from the truck stop to I-84 was completed September 11th.c
  • Minor work remains, including manhole adjustments and striping.