September 3, 2026

  • Signal work at Americana & Shoreline began August 24th and will take 3-4 weeks to complete.
  • Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
  • Concrete sidewalk improvements are complete until signal materials arrive.
  • Milling, paving, and striping are complete.
  • The west leg of Shoreline will remain open to right-in and right-out only traffic and will remain in this configuration until the new traffic signal is complete.
  • The east leg of Shoreline was closed August 24th for the signal work.
Share September 3, 2026 on Facebook Share September 3, 2026 on X (formerly Twitter) Share September 3, 2026 on Linkedin Email September 3, 2026 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>