April 11, 2025

11 Apr 2025
  • Broadway Ave, E 3rd Street to E 6th Street - City utility and storm drain work started at NW 4th. Demo complete. Broadway storm drain installation ongoing. Prepping for concrete.
  • Cherry Ave, NW 4th Street to Meridian Rd - Reopening at the end of this week.
  • Idaho Ave, W 8th St to Meridian Rd.
  • Maple Ave, W 1st Street to Meridian Rd - Reopening at the end of this week.
  • Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
  • E 2nd Street, Idaho Ave to Pine Ave - Concrete placements complete. Asphalt paving this week.
  • E 4th Street, Broadway Ave to State Ave - Milled – intersections are open east/west.
  • W 2nd Street, Cherry Ave to Cherry Lane - Reopening at the end of this week.
  • W 3rd Street, Pine Ave to north end - Site prep ongoing.
  • NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
  • NW 6th Street, Carlton Ave to Washington St.
  • NW 7th Street, McFadden Ave to Washington St.
  • *Irrigation work complete.