- Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - Contractor to set a rolling closure up to start irrigation work, next week.
- Cherry Ave, NW 4th Street to Meridian Rd - Demo/Excavation work ongoing.
- Idaho Ave, W 8th St to Meridian Rd
- Maple Ave, W 1st Street to Meridian Rd - Demo/Excavation work ongoing.
- Washington St, NW 7th Street to Meridian Rd
- E 2nd Street, Idaho Ave to Pine Ave - Demo/Excavation work started.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work ongoing.
- NW 4th Street, Broadway Ave to Maple Ave.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work at various locations is ongoing.
- City of Meridian utility work is ongoing.
Share February 20, 2025 on Facebook
Share February 20, 2025 on Linkedin
Email February 20, 2025 link
- Broadway Ave, E 3rd Street to E 6th Street
- Cherry Ave, NW 4th Street to Meridian Rd - Demo has started.
- Idaho Ave, W 8th St to Meridian Rd o Maple Ave, W 1st Street to Meridian Rd - Demo has started.
- Washington St, NW 7th Street to Meridian Rd
- E 2nd Street, Idaho Ave to Pine Ave - Demo is expected to start next week.
- E 4th Street, Broadway Ave to State Ave
- W 2nd Street, Cherry Ave to Cherry Lane
- W 3rd Street, Pine Ave to north end - Demo has started.
- NW 4th Street, Broadway Ave to Maple Ave - Demo has started.
- NW 6th Street, Carlton Ave to Washington St
- NW 7th Street, McFadden Ave to Washington St
- *Irrigation work has started.
Share February 14, 2025 on Facebook
Share February 14, 2025 on Linkedin
Email February 14, 2025 link
- Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street
- Cherry Ave, NW 4th Street to Meridian Rd - Demo has started.
- Idaho Ave, W 8th St to Meridian Rd
- Maple Ave, W 1st Street to Meridian Rd - Demo has started.
- Washington St, NW 7th Street to Meridian Rd
- E 2nd Street, Idaho Ave to Pine Ave - Demo is expected to start next week.
- E 4th Street, Broadway Ave to State Ave
- W 2nd Street, Cherry Ave to Cherry Lane
- W 3rd Street, Pine Ave to north end - Demo has started.
- NW 4th Street, Broadway Ave to Maple Ave - Demo has started.
- NW 6th Street, Carlton Ave to Washington St
- NW 7th Street, McFadden Ave to Washington St
- *Irrigation work has started.
Share February 13, 2025 - Detour Information - 2nd Street on Facebook
Share February 13, 2025 - Detour Information - 2nd Street on Linkedin
Email February 13, 2025 - Detour Information - 2nd Street link
Starting Monday, February 17, 2025, 2nd Street will be closed from Pine to Idaho until mid March.
Please see the detour map below for more information.

Share February 7, 2025 - Detour Map Information - Broadway - On Hold on Facebook
Share February 7, 2025 - Detour Map Information - Broadway - On Hold on Linkedin
Email February 7, 2025 - Detour Map Information - Broadway - On Hold link
Beginning next week, Broadway Avenue in Meridian will be closed as part of ACHD’s 2025 Meridian Downtown Pavement and Pedestrian Improvements project.
Starting Monday, Broadway Avenue will be closed from East 3rd Street to East 6th Street.
To get around the closure, commuters should use either North Main Street or East 5th Street up to East State Avenue (see detour map).
These roads are expected to reopen at the end of May.

- Broadway Ave, E 3rd Street to E 6th Street
- Cherry Ave, NW 4th Street to Meridian Rd - Road closure has been implemented and contractor has started to mobilize materials.
- Idaho Ave, W 8th St to Meridian Rd
- Maple Ave, W 1st Street to Meridian Rd - Road closure has been implemented and contractor has started to mobilize materials.
- Washington St, NW 7th Street to Meridian Rd o E 2nd Street, Idaho Ave to Pine Ave
- E 4th Street, Broadway Ave to State Ave
- W 2nd Street, Cherry Ave to Cherry Lane
- W 3rd Street, Pine Ave to north end - Road closure has been implemented and contractor has started to mobilize materials.
- NW 4th Street, Broadway Ave to Maple Ave - Road closure has been implemented and contractor has started to mobilize materials.
- NW 6th Street, Carlton Ave to Washington St
- NW 7th Street, McFadden Ave to Washington St
Share January 31, 2025 - Detour Map Information - Maple, Meridian to 1st/NW 4th/NW3rd & Pine on Facebook
Share January 31, 2025 - Detour Map Information - Maple, Meridian to 1st/NW 4th/NW3rd & Pine on Linkedin
Email January 31, 2025 - Detour Map Information - Maple, Meridian to 1st/NW 4th/NW3rd & Pine link
Starting Monday, February 3rd, the following streets will be closed.
- Maple Road from Meridian to W 1st Street
- NW 4th Street from Cherry to Maple
- NW 4th Street from Washington to Idaho
- NW 3rd Street to Pine Ave
Local access will be maintained

Share Construction Starts Late January 2025 on Facebook
Share Construction Starts Late January 2025 on Linkedin
Email Construction Starts Late January 2025 link
The Ada County Highway District (ACHD) will begin construction on the 2025 Meridian Downtown Pavement and Pedestrian Improvements project in late January 2025, with completion expected by fall 2025.
The project includes pavement and pedestrian improvements on the following streets:
- Broadway Avenue, East 3rd Street to East 6th Street
- Cherry Avenue, West 4th Street to Meridian Road
- East 2nd Street, Idaho Avenue to Pine Avenue
- East 4th Street, Broadway Avenue to State Avenue
- Idaho Avenue, West 8th Street to Meridian Road
- Maple Avenue, West 1st Street to Meridian Road
- West 2nd Street, Cherry Avenue to Cherry Lane
- West 3rd Street, Pine Street to North End
- West 4th Street, Broadway Avenue to North of Maple Avenue
- West 5th Street, Carlton Avenue to Washington Street
- West 6th Street, Carlton Avenue to Washington Street
- West 7th Street, Washington Street to the pathway South of McFadden Avenue
- Washington Street, West 7th Street to Meridian Road
Please note that there will also be waterline work on Carlton Avenue between West 6th Street and West 5th Street (see map below).

Expected Construction Impacts:
- Temporary road and lane closures
- Pedestrian detours and sidewalk closures
- Lane restrictions
- General construction noise, dust, equipment backup alarms and ground vibration
- Temporary on-street parking impacts
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts and maintain access
Night work is not anticipated for this project. Additionally, no work will occur on West 1st St., West 4th St., West 7th St., or Washington St. while school is in session unless ACHD grants prior approval. A detailed construction schedule has not yet been submitted by the contractor. For specific questions about the construction schedule once work begins, please contact Nick Wheeler, ACHD Construction Coordinator, at (208)387-6283.
Share Winter 2024 Project Update on Facebook
Share Winter 2024 Project Update on Linkedin
Email Winter 2024 Project Update link
Based on public input and further technical review, the team has made a few changes to the project design.
The improvements now include
- Filling in sidewalk gaps and replacing deteriorated sidewalk to improve connectivity
- Adding bulb-outs and narrowing travel lanes where appropriate to improve safety
- Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA)
- Adding crosswalk markings for school walk route crossings (new)
- Stormwater and irrigation upgrades to improve flows
Street Segments
- West 2nd Street, Camelia Avenue to Cherry Lane
- West 3rd Street, Pine Avenue to the North End
- West 4th Street, Broadway Avenue to Maple Avenue
- Broadway Avenue, East 3rd Street to East 6th Street
- Cherry Avenue, West 4th Street to Meridian Road
- Idaho Avenue, West 8th Street to Meridian Road
- Maple Avenue, West 1st Street to Meridian Road
- East 2nd Street, Idaho Avenue to Pine Avenue (new)
- East 4th Street, Idaho Avenue to State Avenue (new)