2025 Meridian Downtown Pavement and Pedestrian Improvements
The Ada County Highway District (ACHD) will be repaving or reconstructing several streets in Meridian as part of a locally funded project to improve pavement conditions and upgrade the streets for all users.
Work could include
- Filling in sidewalk gaps and replacing deteriorated sidewalk to improve connectivity
- Adding bulb-outs and narrowing travel lanes where appropriate to improve safety
- Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA)
- Adding crosswalk markings for school walk route crossings
- Stormwater and irrigation upgrades to improve flows
Street Segments
- Broadway Avenue, East 3rd Street to East 6th Street
- Cherry Avenue, West 4th Street to Meridian Road
- East 2nd Street, Idaho Avenue to Pine Avenue
- East 4th Street, Broadway Avenue to State Avenue
- Idaho Avenue, West 8th Street to Meridian Road
- Maple Avenue, West 1st Street to Meridian Road
- West 2nd Street, Cherry Avenue to Cherry Lane
- West 3rd Street, Pine Street to North End
- West 4th Street, Broadway Avenue to North of Maple Avenue
- West 5th Street, Carlton Avenue to Washington Street
- West 6th Street, Carlton Avenue to Washington Street
- West 7th Street, Washington Street to the pathway South of McFadden Avenue
- Washington Street, West 7th Street to Meridian Road
To arrange for a translator or other accommodation, contact ACHD at (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org(External link).
Se les recomienda a las personas que necesiten un intérprete o arreglos especiales que llamen a la coordinadora de participación pública, al (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org(External link)
The Ada County Highway District (ACHD) will be repaving or reconstructing several streets in Meridian as part of a locally funded project to improve pavement conditions and upgrade the streets for all users.
Work could include
- Filling in sidewalk gaps and replacing deteriorated sidewalk to improve connectivity
- Adding bulb-outs and narrowing travel lanes where appropriate to improve safety
- Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA)
- Adding crosswalk markings for school walk route crossings
- Stormwater and irrigation upgrades to improve flows
Street Segments
- Broadway Avenue, East 3rd Street to East 6th Street
- Cherry Avenue, West 4th Street to Meridian Road
- East 2nd Street, Idaho Avenue to Pine Avenue
- East 4th Street, Broadway Avenue to State Avenue
- Idaho Avenue, West 8th Street to Meridian Road
- Maple Avenue, West 1st Street to Meridian Road
- West 2nd Street, Cherry Avenue to Cherry Lane
- West 3rd Street, Pine Street to North End
- West 4th Street, Broadway Avenue to North of Maple Avenue
- West 5th Street, Carlton Avenue to Washington Street
- West 6th Street, Carlton Avenue to Washington Street
- West 7th Street, Washington Street to the pathway South of McFadden Avenue
- Washington Street, West 7th Street to Meridian Road
To arrange for a translator or other accommodation, contact ACHD at (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org(External link).
Se les recomienda a las personas que necesiten un intérprete o arreglos especiales que llamen a la coordinadora de participación pública, al (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org(External link)
-
April 11, 2025
Share April 11, 2025 on Facebook Share April 11, 2025 on Twitter Share April 11, 2025 on Linkedin Email April 11, 2025 link11 Apr 2025- Broadway Ave, E 3rd Street to E 6th Street - City utility and storm drain work started at NW 4th. Demo complete. Broadway storm drain installation ongoing. Prepping for concrete.
- Cherry Ave, NW 4th Street to Meridian Rd - Reopening at the end of this week.
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - Reopening at the end of this week.
- Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements complete. Asphalt paving this week.
- E 4th Street, Broadway Ave to State Ave - Milled – intersections are open east/west.
- W 2nd Street, Cherry Ave to Cherry Lane - Reopening at the end of this week.
- W 3rd Street, Pine Ave to north end - Site prep ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.
-
April 4, 2025
Share April 4, 2025 on Facebook Share April 4, 2025 on Twitter Share April 4, 2025 on Linkedin Email April 4, 2025 link04 Apr 2025Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - City utility and storm drain work started at NW 4th. Demo complete. Broadway storm drain installation ongoing. Prepping for concrete.
- Cherry Ave, NW 4th Street to Meridian Rd - Paving this week – reopening next week.
- Idaho Ave, W 8th St to Meridian Rd o Maple Ave, W 1st Street to Meridian Rd - Paving this week – reopening next week.
- Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements complete. Asphalt paving this week.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane - Asphalt paving is scheduled for early next week.
- W 3rd Street, Pine Ave to north end. Site prep ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.
-
March 28, 2025
Share March 28, 2025 on Facebook Share March 28, 2025 on Twitter Share March 28, 2025 on Linkedin Email March 28, 2025 link28 Mar 2025- Broadway Ave, E 3rd Street to E 6th Street - City utility and storm drain work started at NW 4th. Demo complete. Broadway storm drain installation ongoing. Prepping for concrete.
- Cherry Ave, NW 4th Street to Meridian Rd - Grade work and prep complete. Concrete placements ongoing. Asphalt paving is scheduled for next Tuesday.
- Idaho Ave, W 8th St to Meridian Rd o Maple Ave, W 1st Street to Meridian Rd - Grade work and prep complete. Concrete placements ongoing.
- Washington St, NW 7th Street to Meridian Rd - Milling complete.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements complete. Asphalt paving is scheduled for next Tuesday.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane - Asphalt paving is scheduled for next Tuesday.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work complete.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.
-
March 20, 2025
Share March 20, 2025 on Facebook Share March 20, 2025 on Twitter Share March 20, 2025 on Linkedin Email March 20, 2025 link20 Mar 2025- Broadway Ave, E 3rd Street to E 6th Street - Contractor set a closure up (between 4th and 5th) to start irrigation work and demo. City utility and storm drain work started at NW 4th.
- Cherry Ave, NW 4th Street to Meridian Rd - Grade work and prep complete. Concrete placements started.
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - Grade work and prep complete. Concrete placements started.
- Washington St, NW 7th Street to Meridian Rd - Contactor is milling - started on March 17th.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements ongoing.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work started.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.
-
March 14, 2025
Share March 14, 2025 on Facebook Share March 14, 2025 on Twitter Share March 14, 2025 on Linkedin Email March 14, 2025 link14 Mar 2025- Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - Contractor to set a rolling closure up to start irrigation work, possibly next week.City utility and storm drain work to start soon at NW 4th.
- Cherry Ave, NW 4th Street to Meridian Rd - Grade work and prep nearly complete.
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - Grade work and prep nearly complete.
- Washington St, NW 7th Street to Meridian Rd - Contactor is tentatively planning to mill starting on March 17th
- E 2nd Street, Idaho Ave to Pine Ave - Contractor will be starting to place concrete this week for curb, gutter, and sidewalk.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work started.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work at various locations is ongoing – nearly complete
-
March 6, 2025
Share March 6, 2025 on Facebook Share March 6, 2025 on Twitter Share March 6, 2025 on Linkedin Email March 6, 2025 link06 Mar 2025Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - Utility potholing complete. Contractor to set a rolling closure up to start irrigation work, possibly next week.
- Cherry Ave, NW 4th Street to Meridian Rd - Grade work has started.
- Idaho Ave, W 8th St to Meridian Rd
- Maple Ave, W 1st Street to Meridian Rd - Grade work has started.
- Washington St, NW 7th Street to Meridian Rd - Contactor is tentatively planning to mill starting on March 14th.
- E 2nd Street, Idaho Ave to Pine Ave - Demo/Excavation work ongoing.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work ongoing.
- NW 4th Street, Broadway Ave to Maple Ave.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work at various locations is ongoing.
- City of Meridian utility work is ongoing.
-
February 28, 2025
Share February 28, 2025 on Facebook Share February 28, 2025 on Twitter Share February 28, 2025 on Linkedin Email February 28, 2025 link28 Feb 2025- Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - Contractor to set a rolling closure up to start irrigation work, next week.
- Cherry Ave, NW 4th Street to Meridian Rd - Demo/Excavation work ongoing.
- Idaho Ave, W 8th St to Meridian Rd
- Maple Ave, W 1st Street to Meridian Rd - Demo/Excavation work ongoing.
- Washington St, NW 7th Street to Meridian Rd
- E 2nd Street, Idaho Ave to Pine Ave - Demo/Excavation work started.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work ongoing.
- NW 4th Street, Broadway Ave to Maple Ave.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work at various locations is ongoing.
- City of Meridian utility work is ongoing.
-
February 20, 2025
Share February 20, 2025 on Facebook Share February 20, 2025 on Twitter Share February 20, 2025 on Linkedin Email February 20, 2025 link20 Feb 2025- Broadway Ave, E 3rd Street to E 6th Street
- Cherry Ave, NW 4th Street to Meridian Rd - Demo has started.
- Idaho Ave, W 8th St to Meridian Rd o Maple Ave, W 1st Street to Meridian Rd - Demo has started.
- Washington St, NW 7th Street to Meridian Rd
- E 2nd Street, Idaho Ave to Pine Ave - Demo is expected to start next week.
- E 4th Street, Broadway Ave to State Ave
- W 2nd Street, Cherry Ave to Cherry Lane
- W 3rd Street, Pine Ave to north end - Demo has started.
- NW 4th Street, Broadway Ave to Maple Ave - Demo has started.
- NW 6th Street, Carlton Ave to Washington St
- NW 7th Street, McFadden Ave to Washington St
- *Irrigation work has started.
-
February 14, 2025
Share February 14, 2025 on Facebook Share February 14, 2025 on Twitter Share February 14, 2025 on Linkedin Email February 14, 2025 link14 Feb 2025- Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street
- Cherry Ave, NW 4th Street to Meridian Rd - Demo has started.
- Idaho Ave, W 8th St to Meridian Rd
- Maple Ave, W 1st Street to Meridian Rd - Demo has started.
- Washington St, NW 7th Street to Meridian Rd
- E 2nd Street, Idaho Ave to Pine Ave - Demo is expected to start next week.
- E 4th Street, Broadway Ave to State Ave
- W 2nd Street, Cherry Ave to Cherry Lane
- W 3rd Street, Pine Ave to north end - Demo has started.
- NW 4th Street, Broadway Ave to Maple Ave - Demo has started.
- NW 6th Street, Carlton Ave to Washington St
- NW 7th Street, McFadden Ave to Washington St
- *Irrigation work has started.
-
February 13, 2025 - Detour Information - 2nd Street
Share February 13, 2025 - Detour Information - 2nd Street on Facebook Share February 13, 2025 - Detour Information - 2nd Street on Twitter Share February 13, 2025 - Detour Information - 2nd Street on Linkedin Email February 13, 2025 - Detour Information - 2nd Street link13 Feb 2025Starting Monday, February 17, 2025, 2nd Street will be closed from Pine to Idaho until mid March.
Please see the detour map below for more information.
Documents
-
Winter 2024 Update
-
Broadway (E 3rd St to E 6th St).pdf (2.48 MB) (pdf)
-
Cherry (W 4th to Meridian).pdf (4.69 MB) (pdf)
-
E 2nd St (Idaho Ave to Pine Ave).pdf (2.68 MB) (pdf)
-
E 4th Street (Broadway Ave to State Ave).pdf (1.4 MB) (pdf)
-
Idaho (W 8th St to Meridian).pdf (4.7 MB) (pdf)
-
Maple (1st to Meridian).pdf (2.4 MB) (pdf)
-
W 2nd St (Camellia to Cherry Ln).pdf (2.64 MB) (pdf)
-
W 3rd St (Pine to End).pdf (1.92 MB) (pdf)
-
W 4th St (Broadway Ave to Maple Ave).pdf (6 MB) (pdf)
-
W 6th St (W Carlton to W Washington).pdf (2.68 MB) (pdf)
-
Washington (7th to Carlton)_7th (Washington to N).pdf (9.8 MB) (pdf)
-
-
Winter 2022 Public Outreach
-
Winter 2022 Project Information and Project Designs
-
2nd St, Camellia Ave to Cherry Ln Design (1.73 MB) (pdf)
-
3rd St, Pine Ave to End Design (1.18 MB) (pdf)
-
4th St, Broadway Ave to Washington St Design (3.54 MB) (pdf)
-
Broadway Ave, 3rd St to 6th St Design (1.47 MB) (pdf)
-
Idaho Ave, 8th St to 3rd St Design (4.72 MB) (pdf)
-
Maple Ave, 1st St to Meridian Rd Design (1.83 MB) (pdf)
-
Cherry Ave, 4th St to 2nd St Design (3.33 MB) (pdf)
-
Related projects
Live Projects
Follow Project
Who's Listening
-
Sr. Project Manager
Phone 208-387-6100 Email projects@achdidaho.org (External link) -
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org (External link) -
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org (External link)