April 25, 2025
Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - Prepping for concrete. Grade work started.
- Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE.
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - COMPLETE.
- Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - COMPLETE.
- E 4th Street, Broadway Ave to State Ave - Milled – intersections are open east/west. Demo ongoing.
- W 2nd Street, Cherry Ave to Cherry Lane - COMPLETE.
- W 3rd Street, Pine Ave to north end - Site prep ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St - Demo started.
- NW 7th Street, McFadden Ave to Washington St - Demo started.
- *Irrigation work complete.
Share April 25, 2025 on Facebook
Share April 25, 2025 on Twitter
Share April 25, 2025 on Linkedin
Email April 25, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends