April 4, 2025
Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - City utility and storm drain work started at NW 4th. Demo complete. Broadway storm drain installation ongoing. Prepping for concrete.
- Cherry Ave, NW 4th Street to Meridian Rd - Paving this week – reopening next week.
- Idaho Ave, W 8th St to Meridian Rd o Maple Ave, W 1st Street to Meridian Rd - Paving this week – reopening next week.
- Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements complete. Asphalt paving this week.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane - Asphalt paving is scheduled for early next week.
- W 3rd Street, Pine Ave to north end. Site prep ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.