August 1, 2025
- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd - Grade prep complete. Utility work complete. Concrete prep and placements ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- 4th Street, Broadway Ave to State Ave - Demo, utility work, and grade prep complete. Concrete placements complete. Paving this week.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work complete. Concrete complete. Grade prep ongoing.
- W 3rd Street, Pine Ave to north end - Site prep complete. Concrete placements minor work remains. Pine will be closed starting June 24th. Broadway will be the detour. Paving this week.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington St - Demo complete. Utility work complete. Concrete placements ongoing.
- NW 7th Street, McFadden Ave to Washington St - Demo and utility work complete.
Share August 1, 2025 on Facebook
Share August 1, 2025 on X (formerly Twitter)
Share August 1, 2025 on Linkedin
Email August 1, 2025 link
This Project is substantially complete