August 21, 2025

  • Broadway Ave, E 3rd Street to E 6th Street - Complete.
  • Cherry Ave, NW 4th Street to Meridian Rd - Complete.
  • Idaho Ave, W 8th St to Meridian Rd - Milling complete. Demo for sidewalk complete. Working on storm drain installation. Utility work will be completed this week.
  • Maple Ave, W 1st Street to Meridian Rd - Complete.
  • Washington St, NW 7th Street to Meridian Rd - Complete.
  • E 2nd Street, Idaho Ave to Pine Ave - Complete.
  • E 4th Street, Broadway Ave to State Ave - Complete.
  • W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work complete. Concrete placements ongoing. Grade prep ongoing. Working on storm drain install.
  • W 3rd Street, Pine Ave to north end - Complete.
  • NW 4th Street, Broadway Ave to Maple Ave - Complete.
  • NW 6th Street, Carlton Ave to Washington Street - Complete.
  • NW 7th Street, McFadden Ave to Washington St - Complete.