July 18, 2025

Project includes work on the following segments:

  • Broadway Ave, E 3rd Street to E 6th Street - Complete
  • Cherry Ave, NW 4th Street to Meridian Rd - Complete
  • Idaho Ave, W 8th St to Meridian Rd - Complete
  • Maple Ave, W 1st Street to Meridian Rd - Complete
  • Washington St, NW 7th Street to Meridian Rd
    • Grade prep complete.
    • Utility work complete.
    • Concrete prep and placements ongoing.
  • E 2nd Street, Idaho Ave to Pine Ave - Complete
  • E 4th Street, Broadway Ave to State Ave
    • Demo, utility work, and grade prep are ongoing.
    • Concrete placements are ongoing.
  • W 2nd Street, Cherry Ave to Cherry Lane
    • Milling complete.
    • Utility work started.
  • W 3rd Street, Pine Ave to north end
    • Site prep ongoing.
    • Concrete placements have started.
    • Pine will be closed starting June 24th. Broadway will be the detour.
  • NW 4th Street, Broadway Ave to Maple Ave - Complete
  • NW 6th Street, Carlton Ave to Washington St
    • Demo complete.
    • Utility work complete.
    • Concrete placements ongoing.
  • NW 7th Street, McFadden Ave to Washington St
    • Demo and utility work complete.
    • Concrete placements ongoing.
Share July 18, 2025 on Facebook Share July 18, 2025 on X (formerly Twitter) Share July 18, 2025 on Linkedin Email July 18, 2025 link

This Project is substantially complete