June 13, 2025
- Broadway Ave, E 3rd Street to E 6th Street - COMPLETE.
- Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE.
- Idaho Ave, W 8th St to Meridian Rd - Milling started this week.
- Maple Ave, W 1st Street to Meridian Rd - COMPLETE.
- Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work complete. Concrete prep and placements ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - COMPLETE.
- E 4th Street, Broadway Ave to State Ave - Demo, utility work, and grade prep are ongoing. Concrete placements have ongoing.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling started this week.
- W 3rd Street, Pine Ave to north end - Site prep ongoing. Concrete placements have started.
- NW 4th Street, Broadway Ave to Maple Ave - COMPLETE.
- NW 6th Street, Carlton Ave to Washington St - Demo complete. Utility work complete. Concrete placements ongoing.
- NW 7th Street, McFadden Ave to Washington St - Demo and utility work complete. Concrete placements have started.
- *Irrigation work complete.
Share June 13, 2025 on Facebook
Share June 13, 2025 on X (formerly Twitter)
Share June 13, 2025 on Linkedin
Email June 13, 2025 link
This Project is substantially complete