June 20, 2025

21 Jun 2025

Project includes work on the following segments:

  • Broadway Ave, E 3rd Street to E 6th Street
    • COMPLETE
  • Cherry Ave, NW 4th Street to Meridian Rd
    • COMPLETE
  • Idaho Ave, W 8th St to Meridian Rd
    • Milling started this week.
  • Maple Ave, W 1st Street to Meridian Rd
    • COMPLETE
  • Washington St, NW 7th Street to Meridian Rd
    • Grade prep and demo ongoing.
    • Utility work complete.
    • Concrete prep and placements ongoing.
  • E 2nd Street, Idaho Ave to Pine Ave
    • COMPLETE
  • E 4th Street, Broadway Ave to State Ave
    • Demo, utility work, and grade prep are ongoing
    • Concrete placements have ongoing
  • W 2nd Street, Cherry Ave to Cherry Lane
    • Milling started this week.
  • W 3rd Street, Pine Ave to north end
    • Site prep ongoing.
    • Concrete placements have started.
    • Pine will be closed starting next week. Broadway will be the detour.
  • NW 4th Street, Broadway Ave to Maple Ave
    • COMPLETE
  • NW 6th Street, Carlton Ave to Washington St
    • Demo complete.
    • Utility work complete.
    • Concrete placements ongoing.
  • NW 7th Street, McFadden Ave to Washington St
    • Demo and utility work complete.
    • Concrete placements have started.
Share June 20, 2025 on Facebook Share June 20, 2025 on Twitter Share June 20, 2025 on Linkedin Email June 20, 2025 link
#<Object:0x000000003bd0f148>