June 20, 2025
Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street
- COMPLETE
- Cherry Ave, NW 4th Street to Meridian Rd
- COMPLETE
- Idaho Ave, W 8th St to Meridian Rd
- Milling started this week.
- Maple Ave, W 1st Street to Meridian Rd
- COMPLETE
- Washington St, NW 7th Street to Meridian Rd
- Grade prep and demo ongoing.
- Utility work complete.
- Concrete prep and placements ongoing.
- E 2nd Street, Idaho Ave to Pine Ave
- COMPLETE
- E 4th Street, Broadway Ave to State Ave
- Demo, utility work, and grade prep are ongoing
- Concrete placements have ongoing
- W 2nd Street, Cherry Ave to Cherry Lane
- Milling started this week.
- W 3rd Street, Pine Ave to north end
- Site prep ongoing.
- Concrete placements have started.
- Pine will be closed starting next week. Broadway will be the detour.
- NW 4th Street, Broadway Ave to Maple Ave
- COMPLETE
- NW 6th Street, Carlton Ave to Washington St
- Demo complete.
- Utility work complete.
- Concrete placements ongoing.
- NW 7th Street, McFadden Ave to Washington St
- Demo and utility work complete.
- Concrete placements have started.
Share June 20, 2025 on Facebook
Share June 20, 2025 on Twitter
Share June 20, 2025 on Linkedin
Email June 20, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends