June 6, 2025
- Broadway Ave, E 3rd Street to E 6th Street - Paving this week.
- Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE.
- Idaho Ave, W 8th St to Meridian Rd - Work starting June 9th.
- Maple Ave, W 1st Street to Meridian Rd -COMPLETE.
- Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work complete. Concrete placements have started.
- E 2nd Street, Idaho Ave to Pine Ave - COMPLETE.
- E 4th Street, Broadway Ave to State Ave - Demo, utility work, and grade prep are ongoing. Concrete placements have started.
- W 2nd Street, Cherry Ave to Cherry Lane - COMPLETE.
- W 3rd Street, Pine Ave to north end. Site prep ongoing. Concrete placements have started.
- NW 4th Street, Broadway Ave to Maple Ave - Paving complete.
- NW 6th Street, Carlton Ave to Washington St - Demo complete. Utility work complete. Concrete placements have started.
- NW 7th Street, McFadden Ave to Washington St - Demo and utility work complete. Concrete placements have started.
- *Irrigation work complete.
Share June 6, 2025 on Facebook
Share June 6, 2025 on Twitter
Share June 6, 2025 on Linkedin
Email June 6, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends