- Broadway Ave, E 3rd Street to E 6th Street - Contractor set a closure up (between 4th and 5th) to start irrigation work and demo. City utility and storm drain work started at NW 4th.
- Cherry Ave, NW 4th Street to Meridian Rd - Grade work and prep complete. Concrete placements started.
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - Grade work and prep complete. Concrete placements started.
- Washington St, NW 7th Street to Meridian Rd - Contactor is milling - started on March 17th.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements ongoing.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work started.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.
Share March 20, 2025 on Facebook
Share March 20, 2025 on Twitter
Share March 20, 2025 on Linkedin
Email March 20, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends