March 20, 2025
- Broadway Ave, E 3rd Street to E 6th Street - Contractor set a closure up (between 4th and 5th) to start irrigation work and demo. City utility and storm drain work started at NW 4th.
- Cherry Ave, NW 4th Street to Meridian Rd - Grade work and prep complete. Concrete placements started.
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - Grade work and prep complete. Concrete placements started.
- Washington St, NW 7th Street to Meridian Rd - Contactor is milling - started on March 17th.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements ongoing.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work started.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.