March 28, 2025
- Broadway Ave, E 3rd Street to E 6th Street - City utility and storm drain work started at NW 4th. Demo complete. Broadway storm drain installation ongoing. Prepping for concrete.
- Cherry Ave, NW 4th Street to Meridian Rd - Grade work and prep complete. Concrete placements ongoing. Asphalt paving is scheduled for next Tuesday.
- Idaho Ave, W 8th St to Meridian Rd o Maple Ave, W 1st Street to Meridian Rd - Grade work and prep complete. Concrete placements ongoing.
- Washington St, NW 7th Street to Meridian Rd - Milling complete.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements complete. Asphalt paving is scheduled for next Tuesday.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane - Asphalt paving is scheduled for next Tuesday.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work complete.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.
Share March 28, 2025 on Facebook
Share March 28, 2025 on Twitter
Share March 28, 2025 on Linkedin
Email March 28, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends