October 10, 2025
- Broadway Ave, E 3rd Street to E 6th Street - Complete
- Cherry Ave, NW 4th Street to Meridian Rd - Complete
- Idaho Ave, W 8th St to Meridian Rd - Paving complete from 3rd west. Sidewalk, curb and gutter ongoing to the east. Next pave date is scheduled for Oct 15 and 16. Landscaping and sidewalk work ongoing.
- Maple Ave, W 1st Street to Meridian Rd - Complete
- Washington St, NW 7th Street to Meridian Rd - Complete
- E 2nd Street, Idaho Ave to Pine Ave - Complete
- E 4th Street, Broadway Ave to State Ave - Complete
- W 2nd Street, Cherry Ave to Cherry Lane - Paved on September 30th. Landscape repair ongoing.
- W 3rd Street, Pine Ave to north end - Complete
- NW 4th Street, Broadway Ave to Maple Ave - Complete
- NW 6th Street, Carlton Ave to Washington St - Complete
- NW 7th Street, McFadden Ave to Washington St - Complete
Share October 10, 2025 on Facebook
Share October 10, 2025 on Twitter
Share October 10, 2025 on Linkedin
Email October 10, 2025 link
This Project is substantially complete