22nd Street and Ridenbaugh Street Storm Drain Project

Share 22nd Street and Ridenbaugh Street Storm Drain Project on Facebook Share 22nd Street and Ridenbaugh Street Storm Drain Project on Twitter Share 22nd Street and Ridenbaugh Street Storm Drain Project on Linkedin Email 22nd Street and Ridenbaugh Street Storm Drain Project link

Project is substantially complete. 

The Ada County Highway District (ACHD) will begin construction on the 22nd Street & Ridenbaugh Street project in September of 2023. Construction is expected to be completed in November of 2023.

The project will include updating storm drain facilities and installing a new storm drain pipe on 22nd Street from Ridenbaugh Street to Lemp Street, as the existing facilities are currently failing. In addition to this work, the contractor will also be constructing bulb-outs at the intersection of 22nd Street and Ridenbaugh.

Construction Impacts:

  • For some driveways, there may be a need for a short-duration closure while work is occurring directly in front of the driveway
  • General construction noise, dust, equipment backup alarms, and ground vibration
  • Crews will work from 7 a.m. to 6 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize construction impacts

The Ada County Highway District (ACHD) will begin construction on the 22nd Street & Ridenbaugh Street project in September of 2023. Construction is expected to be completed in November of 2023.

The project will include updating storm drain facilities and installing a new storm drain pipe on 22nd Street from Ridenbaugh Street to Lemp Street, as the existing facilities are currently failing. In addition to this work, the contractor will also be constructing bulb-outs at the intersection of 22nd Street and Ridenbaugh.

Construction Impacts:

  • For some driveways, there may be a need for a short-duration closure while work is occurring directly in front of the driveway
  • General construction noise, dust, equipment backup alarms, and ground vibration
  • Crews will work from 7 a.m. to 6 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize construction impacts

Project is substantially complete. 

  • December 1, 2023

    Share December 1, 2023 on Facebook Share December 1, 2023 on Twitter Share December 1, 2023 on Linkedin Email December 1, 2023 link

    Project is substantially complete.

  • November 22, 2023

    Share November 22, 2023 on Facebook Share November 22, 2023 on Twitter Share November 22, 2023 on Linkedin Email November 22, 2023 link
    • Pipe work and concrete work are complete.
    • Asphalt paving was completed November 7th.
    • Minor work remains, including manhole adjustments and minor concrete repair
  • November 17, 2023

    Share November 17, 2023 on Facebook Share November 17, 2023 on Twitter Share November 17, 2023 on Linkedin Email November 17, 2023 link

    Pipe work and concrete work are complete.

    Asphalt paving was completed November 7th .

    Minor work remains, including manhole adjustments and minor concrete repair.

  • November 9, 2023

    Share November 9, 2023 on Facebook Share November 9, 2023 on Twitter Share November 9, 2023 on Linkedin Email November 9, 2023 link
    • Pipe work and concrete work are complete.
    • Asphalt paving was completed November 7th.
    • Minor work remains, including manhole adjustments and minor concrete repair.
  • November 3, 2023

    Share November 3, 2023 on Facebook Share November 3, 2023 on Twitter Share November 3, 2023 on Linkedin Email November 3, 2023 link
    • Intermountain Gas relocating utility on 26th Street.
    • Lumen working on utility work at 26th Street.
  • October 27, 2023

    Share October 27, 2023 on Facebook Share October 27, 2023 on Twitter Share October 27, 2023 on Linkedin Email October 27, 2023 link
    • The road is closed for the duration of the work.
    • Pipe work and concrete work are complete; contractor working on roadway improvements.
    • Asphalt paving is scheduled for October 30th, weather permitting.
  • October 20, 2023

    Share October 20, 2023 on Facebook Share October 20, 2023 on Twitter Share October 20, 2023 on Linkedin Email October 20, 2023 link
    • The road is closed for the duration of the work.
    • Pipe work is complete; contractor working on sidewalk and roadway improvements.
  • October 12, 2023

    Share October 12, 2023 on Facebook Share October 12, 2023 on Twitter Share October 12, 2023 on Linkedin Email October 12, 2023 link
    • Road is closed for the duration of the work.
    • Pipe work is complete. Contractor working on sidewalk and roadway improvements.
  • October 6, 2023

    Share October 6, 2023 on Facebook Share October 6, 2023 on Twitter Share October 6, 2023 on Linkedin Email October 6, 2023 link
    • Contractor started work on September 25th.
    • The road is closed for duration of the work.