November 9, 2023

  • Pipe work and concrete work are complete.
  • Asphalt paving was completed November 7th.
  • Minor work remains, including manhole adjustments and minor concrete repair.
Share November 9, 2023 on Facebook Share November 9, 2023 on Twitter Share November 9, 2023 on Linkedin Email November 9, 2023 link

Project is substantially complete. 