32nd Street and Clay Street Projects

Share 32nd Street and Clay Street Projects on Facebook Share 32nd Street and Clay Street Projects on Twitter Share 32nd Street and Clay Street Projects on Linkedin Email 32nd Street and Clay Street Projects link

The Ada County Highway District (ACHD), in partnership with Garden City and the Garden City Urban Renewal Agency (URA), is designing changes for Clay Street, 37th Street to 32nd Street & 32nd Street, Chinden Boulevard to Clay Street.

The purpose of these projects is to accommodate a growing Garden City and provide increased pedestrian connectivity and safety.

Project Description

  • Reconstruct Clay and 32nd streets.
  • Add curb, gutter and sidewalk on both sides of Clay and 32nd streets to provide a dedicated space for pedestrians.
  • Replace most existing sidewalk.
  • Construct bulb-outs to help slow traffic and increase safety.
  • Install street lighting for safety.
  • Most on-street parking will remain on both sides of the streets.

The Ada County Highway District (ACHD), in partnership with Garden City and the Garden City Urban Renewal Agency (URA), is designing changes for Clay Street, 37th Street to 32nd Street & 32nd Street, Chinden Boulevard to Clay Street.

The purpose of these projects is to accommodate a growing Garden City and provide increased pedestrian connectivity and safety.

Project Description

  • Reconstruct Clay and 32nd streets.
  • Add curb, gutter and sidewalk on both sides of Clay and 32nd streets to provide a dedicated space for pedestrians.
  • Replace most existing sidewalk.
  • Construct bulb-outs to help slow traffic and increase safety.
  • Install street lighting for safety.
  • Most on-street parking will remain on both sides of the streets.
  • CLOSED: This survey has concluded.

    After reviewing the information for the Clay and 32nd Streets projects, fill out the community feedback survey!

    Share What do you think of the Clay and 32nd projects? on Facebook Share What do you think of the Clay and 32nd projects? on Twitter Share What do you think of the Clay and 32nd projects? on Linkedin Email What do you think of the Clay and 32nd projects? link
Page last updated: 12 Jul 2024, 11:15 AM