  • Avenue C between Main Street and 4th Street will be closed for the duration of the project.
  • Concrete curb, gutter and sidewalk work is complete.
  • Contractor placing brick pavers.
  • Asphalt paving was done April 12th.
Share April 14, 2023 on Facebook Share April 14, 2023 on Twitter Share April 14, 2023 on Linkedin Email April 14, 2023 link

This project is substantially complete.