Avenue C, Main Street to 4th Street

Share Avenue C, Main Street to 4th Street on Facebook Share Avenue C, Main Street to 4th Street on Twitter Share Avenue C, Main Street to 4th Street on Linkedin Email Avenue C, Main Street to 4th Street link

This project is substantially complete.

In early January, the Ada County Highway District (ACHD) will start construction on Avenue C from Main Street to 4th Street in Kuna. Construction is anticipated to be completed in May of 2023.

Project Description

  • Construct new angled or parallel parking and sidewalks on both sides of Avenue C
  • Upgrade pedestrian ramps to meet modern standards
  • As part of this project, ACHD will also reconstruct Avenue C from Main Street to 4th Street

Construction Impacts

  • Temporary road closures (business access will be maintained)
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize construction impacts


Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk. 

In early January, the Ada County Highway District (ACHD) will start construction on Avenue C from Main Street to 4th Street in Kuna. Construction is anticipated to be completed in May of 2023.

Project Description

  • Construct new angled or parallel parking and sidewalks on both sides of Avenue C
  • Upgrade pedestrian ramps to meet modern standards
  • As part of this project, ACHD will also reconstruct Avenue C from Main Street to 4th Street

Construction Impacts

  • Temporary road closures (business access will be maintained)
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize construction impacts


Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk. 

This project is substantially complete.

  • April 21, 2023

    Share April 21, 2023 on Facebook Share April 21, 2023 on Twitter Share April 21, 2023 on Linkedin Email April 21, 2023 link
    • Avenue C will be closed between Main Street and 4th Street for the duration of the project.
    • Concrete curb, gutter and sidewalk work is complete. Asphalt paving is complete.
    • Contractor placing brick pavers - ongoing.
  • April 14, 2023

    Share April 14, 2023 on Facebook Share April 14, 2023 on Twitter Share April 14, 2023 on Linkedin Email April 14, 2023 link
    • Avenue C between Main Street and 4th Street will be closed for the duration of the project.
    • Concrete curb, gutter and sidewalk work is complete.
    • Contractor placing brick pavers.
    • Asphalt paving was done April 12th.
  • April 7, 2023

    Share April 7, 2023 on Facebook Share April 7, 2023 on Twitter Share April 7, 2023 on Linkedin Email April 7, 2023 link
    • Avenue C will be closed between Main Street and 4th Street for the duration of the project.
    • Concrete curb, gutter, and sidewalk work is complete.
    • Contractor placing brick pavers.
    • Asphalt paving is scheduled for mid-April.
  • March 31, 2023

    Share March 31, 2023 on Facebook Share March 31, 2023 on Twitter Share March 31, 2023 on Linkedin Email March 31, 2023 link
    • Avenue C will be closed between Main Street and 4th Street for the duration of the project.
    • Concrete curb, gutter and sidewalk work is complete.
    • Contractor placing brick pavers.
    • Asphalt paving is scheduled for mid-April.
  • March 24, 2023

    Share March 24, 2023 on Facebook Share March 24, 2023 on Twitter Share March 24, 2023 on Linkedin Email March 24, 2023 link
    • Avenue C will be closed between Main Street and 4th Street for the duration of the project.
    • Concrete curb, gutter and sidewalk work is complete.
    • Contractor prepping for placement of brick pavers.
  • March 17, 2023

    Share March 17, 2023 on Facebook Share March 17, 2023 on Twitter Share March 17, 2023 on Linkedin Email March 17, 2023 link
    • Avenue C will be closed between Main Street and 4th Street for the duration of the project.
    • Contractor placing curb, gutter and sidewalk.
    • Contractor prepping for placement of brick pavers.
  • March 10, 2023

    Share March 10, 2023 on Facebook Share March 10, 2023 on Twitter Share March 10, 2023 on Linkedin Email March 10, 2023 link
    • Avenue C will be closed between Main Street and 4th Street for the duration of the project.
    • Contractor placing curb, gutter and sidewalk.
    • Contractor prepping for placement of brick pavers.
  • March 3, 2023

    Share March 3, 2023 on Facebook Share March 3, 2023 on Twitter Share March 3, 2023 on Linkedin Email March 3, 2023 link
    • Avenue C will be closed between Main Street. 4th Street for the duration of the project.
    • Contractor placing curb, gutter and sidewalk.
  • February 24, 2023

    Share February 24, 2023 on Facebook Share February 24, 2023 on Twitter Share February 24, 2023 on Linkedin Email February 24, 2023 link
    • Avenue C will be closed between Main and 4th Street for the duration of the project.
    • Contractor placing curb, gutter and sidewalk.
  • February 17, 2023

    Share February 17, 2023 on Facebook Share February 17, 2023 on Twitter Share February 17, 2023 on Linkedin Email February 17, 2023 link
    • Avenue C is closed between Main Street and 4th Street for the duration of the project.
    • Contractor prepping for concrete curb and gutter.