-
Share April 21, 2023 on Facebook
Share April 21, 2023 on X (formerly Twitter)
Share April 21, 2023 on Linkedin
Email April 21, 2023 link
- Avenue C will be closed between Main Street and 4th Street for the duration of the project.
- Concrete curb, gutter and sidewalk work is complete. Asphalt paving is complete.
- Contractor placing brick pavers - ongoing.
- Avenue C will be closed between Main Street and 4th Street for the duration of the project.
- Concrete curb, gutter and sidewalk work is complete. Asphalt paving is complete.
- Contractor placing brick pavers - ongoing.
This project is substantially complete.
-
Share April 14, 2023 on Facebook
Share April 14, 2023 on X (formerly Twitter)
Share April 14, 2023 on Linkedin
Email April 14, 2023 link
- Avenue C between Main Street and 4th Street will be closed for the duration of the project.
- Concrete curb, gutter and sidewalk work is complete.
- Contractor placing brick pavers.
- Asphalt paving was done April 12th.
- Avenue C between Main Street and 4th Street will be closed for the duration of the project.
- Concrete curb, gutter and sidewalk work is complete.
- Contractor placing brick pavers.
- Asphalt paving was done April 12th.
This project is substantially complete.
-
Share April 7, 2023 on Facebook
Share April 7, 2023 on X (formerly Twitter)
Share April 7, 2023 on Linkedin
Email April 7, 2023 link
- Avenue C will be closed between Main Street and 4th Street for the duration of the project.
- Concrete curb, gutter, and sidewalk work is complete.
- Contractor placing brick pavers.
- Asphalt paving is scheduled for mid-April.
- Avenue C will be closed between Main Street and 4th Street for the duration of the project.
- Concrete curb, gutter, and sidewalk work is complete.
- Contractor placing brick pavers.
- Asphalt paving is scheduled for mid-April.
This project is substantially complete.
-
Share March 31, 2023 on Facebook
Share March 31, 2023 on X (formerly Twitter)
Share March 31, 2023 on Linkedin
Email March 31, 2023 link
- Avenue C will be closed between Main Street and 4th Street for the duration of the project.
- Concrete curb, gutter and sidewalk work is complete.
- Contractor placing brick pavers.
- Asphalt paving is scheduled for mid-April.
- Avenue C will be closed between Main Street and 4th Street for the duration of the project.
- Concrete curb, gutter and sidewalk work is complete.
- Contractor placing brick pavers.
- Asphalt paving is scheduled for mid-April.
This project is substantially complete.
-
Share March 24, 2023 on Facebook
Share March 24, 2023 on X (formerly Twitter)
Share March 24, 2023 on Linkedin
Email March 24, 2023 link
- Avenue C will be closed between Main Street and 4th Street for the duration of the project.
- Concrete curb, gutter and sidewalk work is complete.
- Contractor prepping for placement of brick pavers.
- Avenue C will be closed between Main Street and 4th Street for the duration of the project.
- Concrete curb, gutter and sidewalk work is complete.
- Contractor prepping for placement of brick pavers.
This project is substantially complete.
-
Share March 17, 2023 on Facebook
Share March 17, 2023 on X (formerly Twitter)
Share March 17, 2023 on Linkedin
Email March 17, 2023 link
- Avenue C will be closed between Main Street and 4th Street for the duration of the project.
- Contractor placing curb, gutter and sidewalk.
- Contractor prepping for placement of brick pavers.
- Avenue C will be closed between Main Street and 4th Street for the duration of the project.
- Contractor placing curb, gutter and sidewalk.
- Contractor prepping for placement of brick pavers.
This project is substantially complete.
-
Share March 10, 2023 on Facebook
Share March 10, 2023 on X (formerly Twitter)
Share March 10, 2023 on Linkedin
Email March 10, 2023 link
- Avenue C will be closed between Main Street and 4th Street for the duration of the project.
- Contractor placing curb, gutter and sidewalk.
- Contractor prepping for placement of brick pavers.
- Avenue C will be closed between Main Street and 4th Street for the duration of the project.
- Contractor placing curb, gutter and sidewalk.
- Contractor prepping for placement of brick pavers.
This project is substantially complete.
-
Share March 3, 2023 on Facebook
Share March 3, 2023 on X (formerly Twitter)
Share March 3, 2023 on Linkedin
Email March 3, 2023 link
- Avenue C will be closed between Main Street. 4th Street for the duration of the project.
- Contractor placing curb, gutter and sidewalk.
- Avenue C will be closed between Main Street. 4th Street for the duration of the project.
- Contractor placing curb, gutter and sidewalk.
This project is substantially complete.
-
Share February 24, 2023 on Facebook
Share February 24, 2023 on X (formerly Twitter)
Share February 24, 2023 on Linkedin
Email February 24, 2023 link
- Avenue C will be closed between Main and 4th Street for the duration of the project.
- Contractor placing curb, gutter and sidewalk.
- Avenue C will be closed between Main and 4th Street for the duration of the project.
- Contractor placing curb, gutter and sidewalk.
This project is substantially complete.
-
Share February 17, 2023 on Facebook
Share February 17, 2023 on X (formerly Twitter)
Share February 17, 2023 on Linkedin
Email February 17, 2023 link
- Avenue C is closed between Main Street and 4th Street for the duration of the project.
- Contractor prepping for concrete curb and gutter.
- Avenue C is closed between Main Street and 4th Street for the duration of the project.
- Contractor prepping for concrete curb and gutter.
This project is substantially complete.