April 21, 2023

  • Avenue C will be closed between Main Street and 4th Street for the duration of the project.
  • Concrete curb, gutter and sidewalk work is complete. Asphalt paving is complete.
  • Contractor placing brick pavers - ongoing.
Share April 21, 2023 on Facebook Share April 21, 2023 on Twitter Share April 21, 2023 on Linkedin Email April 21, 2023 link

This project is substantially complete.