March 31, 2023

31 Mar 2023
  • Avenue C will be closed between Main Street and 4th Street for the duration of the project.
  • Concrete curb, gutter and sidewalk work is complete.
  • Contractor placing brick pavers.
  • Asphalt paving is scheduled for mid-April.
Share March 31, 2023 on Facebook Share March 31, 2023 on Twitter Share March 31, 2023 on Linkedin Email March 31, 2023 link

This project is substantially complete.