April 21, 2023

  • Box culvert was set March 16th.
  • Concrete wingwalls are complete.
  • Paving anticipated on April 20th.
  • Anticipated opening by April 28th.
Share April 21, 2023 on Facebook Share April 21, 2023 on X (formerly Twitter) Share April 21, 2023 on Linkedin Email April 21, 2023 link

This project is substantially complete.