- Box culvert is complete.
- Anticipated opening roadway by April 28th.
- Box culvert is complete.
- Anticipated opening roadway by April 28th.
This project is substantially complete.
-
Share April 21, 2023 on Facebook
Share April 21, 2023 on X (formerly Twitter)
Share April 21, 2023 on Linkedin
Email April 21, 2023 link
- Box culvert was set March 16th.
- Concrete wingwalls are complete.
- Paving anticipated on April 20th.
- Anticipated opening by April 28th.
- Box culvert was set March 16th.
- Concrete wingwalls are complete.
- Paving anticipated on April 20th.
- Anticipated opening by April 28th.
This project is substantially complete.
-
Share April 14, 2023 on Facebook
Share April 14, 2023 on X (formerly Twitter)
Share April 14, 2023 on Linkedin
Email April 14, 2023 link
- Box culvert was set March 16th.
- Concrete wingwalls are complete.
- Grade work ongoing.
- Road prep and paving anticipated by April 21st.
- Box culvert was set March 16th.
- Concrete wingwalls are complete.
- Grade work ongoing.
- Road prep and paving anticipated by April 21st.
This project is substantially complete.
-
Share April 7, 2023 on Facebook
Share April 7, 2023 on X (formerly Twitter)
Share April 7, 2023 on Linkedin
Email April 7, 2023 link
- Box culvert was set March 16th.
- Concrete wingwalls are complete.
- Backfill ongoing.
- Road prep and paving anticipated April 11th.
- Box culvert was set March 16th.
- Concrete wingwalls are complete.
- Backfill ongoing.
- Road prep and paving anticipated April 11th.
This project is substantially complete.
-
Share March 31, 2023 on Facebook
Share March 31, 2023 on X (formerly Twitter)
Share March 31, 2023 on Linkedin
Email March 31, 2023 link
- Box culvert was set March 16th.
- Concrete wingwalls will be complete August 29th.
- Backfill scheduled for the week of April 1st.
- Box culvert was set March 16th.
- Concrete wingwalls will be complete August 29th.
- Backfill scheduled for the week of April 1st.
This project is substantially complete.
-
Share March 24, 2023 on Facebook
Share March 24, 2023 on X (formerly Twitter)
Share March 24, 2023 on Linkedin
Email March 24, 2023 link
- Irrigation boxes installed.
- Box culvert was set March 16th.
- Concrete wingwalls complete March 24th.
- Backfill scheduled for the week of March 27th.
- Irrigation boxes installed.
- Box culvert was set March 16th.
- Concrete wingwalls complete March 24th.
- Backfill scheduled for the week of March 27th.
This project is substantially complete.
-
Share March 17, 2023 on Facebook
Share March 17, 2023 on X (formerly Twitter)
Share March 17, 2023 on Linkedin
Email March 17, 2023 link
- Irrigation boxes installed.
- Bridge removed and excavated.
- Prepping for headwalls. Placing concrete starting March 9th.
- Road removed.
- Boxes set starting March 16th.
- Irrigation boxes installed.
- Bridge removed and excavated.
- Prepping for headwalls. Placing concrete starting March 9th.
- Road removed.
- Boxes set starting March 16th.
This project is substantially complete.
-
Share March 10, 2023 on Facebook
Share March 10, 2023 on X (formerly Twitter)
Share March 10, 2023 on Linkedin
Email March 10, 2023 link
- Irrigation boxes installed.
- Bridge removed and excavated.
- Prepping for headwalls. Placing concrete starting March 9th.
- Road removed.
- Boxes planned to be set March 16th.
- Irrigation boxes installed.
- Bridge removed and excavated.
- Prepping for headwalls. Placing concrete starting March 9th.
- Road removed.
- Boxes planned to be set March 16th.
This project is substantially complete.
-
Share March 3, 2023 on Facebook
Share March 3, 2023 on X (formerly Twitter)
Share March 3, 2023 on Linkedin
Email March 3, 2023 link
- Irrigation boxes installed.
- Bridge removed and excavated.
- Prepping for headwalls - waiting on concrete subcontractor.
- Road removed.
- Irrigation boxes installed.
- Bridge removed and excavated.
- Prepping for headwalls - waiting on concrete subcontractor.
- Road removed.
This project is substantially complete.
-
Share February 24, 2023 on Facebook
Share February 24, 2023 on X (formerly Twitter)
Share February 24, 2023 on Linkedin
Email February 24, 2023 link
- Irrigation boxes installed.
- Bridge removed and excavated.
- Prepping for headwalls - placement anticipated by the 24th.
- Road removed.
- Irrigation boxes installed.
- Bridge removed and excavated.
- Prepping for headwalls - placement anticipated by the 24th.
- Road removed.
This project is substantially complete.