March 10, 2023

  • Irrigation boxes installed.
  • Bridge removed and excavated.
  • Prepping for headwalls. Placing concrete starting March 9th.
  • Road removed.
  • Boxes planned to be set March 16th.
Share March 10, 2023 on Facebook Share March 10, 2023 on Twitter Share March 10, 2023 on Linkedin Email March 10, 2023 link

This project is substantially complete.